July 30, 2019

Board discussed the erosion on the north side of the drainage flume north of the Amethyst cul-de-sac. Rusty Kraybill proposed extending the south curb of the flume 10 -15 feet south to eliminate the 90 turn and requested bids, only one bid was submitted. The bid was from K&L Concrete for $3,874. It did not include the re-positioning of erosion stones that have moved down stream. Rusty estimates that the re-positioning will cost an additional $300. Amanda Aker moved to approve $4,274 for the repair of the drainage flume and rock re positioning. Randy Seales seconded the motion. The repair to the drainage flume was approved.